Smurfit Kappa Nettingsdorfer Papierfabrik AG & CO KG - Haid / Ansfelden - 2003

Erection medium voltage power distribution system, Austria

Client: Smurfit Kappa Nettingsdorfer Papierfabrik AG & Co KG, Haid / Ansfelden, Austria

Erection medium voltage power distribution system

10 kV resp. 3 kV


Project

TBP received the order to build the new medium-voltage system for power distribution within an extremely short timeframe and in amicable cooperation with the customer and suppliers. 


Planning contract

  • System concept
  • Specification of the structural requirements
  • Construction of a new control room 36 x 9 x 8 m incl. cable floor
  • (+15 m above the existing electrical control center)
  • Tender for medium-voltage system and electrical installation
  • Implementation of an energy control system
  • Time scheduling


Technical data

Switch room                                                 36 x 9 x 8 m (incl. cable base) 
Medium-voltage system 53 rows
10 kV cable 7.000 m
10 kV terminations or joints 250 pieces



Implementation period

Award of contract and specification           Dec 2002
Award of the medium-voltage system Feb 2003
Permitting procedure Mar 2003
Supply of the switchgear Jul 2003
Switchgear rede for operation Aug 2003
Cable connection Aug 2003 - Sep 2003


Following projects:

  • 2007 - Mechanical engineering for the conversion of the PM6 drives (P4566)
  • 2017 - Project upgrade energy plant (P00539)