PLANTENGINEERING
Smurfit Kappa Nettingsdorfer Papierfabrik AG & CO KG - Haid / Ansfelden - 2003
Erection medium voltage power distribution system, Austria
Client: Smurfit Kappa Nettingsdorfer Papierfabrik AG & Co KG, Haid / Ansfelden, Austria
Erection medium voltage power distribution system
10 kV resp. 3 kV
Project
TBP received the order to build the new medium-voltage system for power distribution within an extremely short timeframe and in amicable cooperation with the customer and suppliers.
Planning contract
- System concept
- Specification of the structural requirements
- Construction of a new control room 36 x 9 x 8 m incl. cable floor
- (+15 m above the existing electrical control center)
- Tender for medium-voltage system and electrical installation
- Implementation of an energy control system
- Time scheduling
Technical data
| Switch room | 36 x 9 x 8 m (incl. cable base) |
| Medium-voltage system | 53 rows |
| 10 kV cable | 7.000 m |
| 10 kV terminations or joints | 250 pieces |
Implementation period
| Award of contract and specification | Dec 2002 |
| Award of the medium-voltage system | Feb 2003 |
| Permitting procedure | Mar 2003 |
| Supply of the switchgear | Jul 2003 |
| Switchgear rede for operation | Aug 2003 |
| Cable connection | Aug 2003 - Sep 2003 |
Following projects:
- 2007 - Mechanical engineering for the conversion of the PM6 drives (P4566)
- 2017 - Project upgrade energy plant (P00539)