Laakirchen Papier AG - Laakirchen - 2016

Submission planning „Renil PM10“ and expansion PM11, Austria

Client: Laakirchen Papier AG, Laakirchen, Austria

Submission planning “Renil PM10” and expansion PM11

350.000 t/y net (after expansion PM11) / 450.000 t/y net (after rebuilt PM10)


Project

TBP received the order for the rebuild of paper machine PM10 to liner as well as the removal of paper machine PM11. The scope of the expansion work includes the calender 5 (6/8 rolls), the hall crane for the extension, the adaptation of the RSM 3, the tamour cross transport, the connection to existing burners for roll heating, the adaptation of the hall ventilation, the adaptation of the edge trim suction system, and the adaptation of the workshop tract.


Planning contract

  • Documents for the preliminary with authorities
  • Basic-engineering

    • Schedule planning
    • Process engineering
    • System engineering
    • Electric-concept
    • Automation and instrumentation concept
  • Commercial submission planning “Renil PM10”

    • Layouts
    • Project description
    • Emission layout
    • Logistics
    • Block diagram
    • Consumption values
    • Participation in meetings with authoritie

Project size

Investment sum approx. 100 Mio €
thereof expansion PM10                                                approx.     6 Mio €

 

Technical Data

Production after expansion PM10 production line 350.000 t/y
Products

Packaging papers (recycled containerboard
(Corrugating medium, Testliner))
Trimed width according to PM 7.500 mm
Stock preparation 2-layer

 

Raw materials 1.02 (B12); 1.04 (B19); 4.03 (W52)
Waste paper stock preparation capacity 1.300 t/d (bone dry)
Storage for waste paper 15.000 t/d (target value 20.000 t/d)
Stock of finished goods 15.000 t/d SC paper


Implementation period

Documents for the preliminary with authorities Feb 2015 - Apr 2015
Basic-engineering and permitting documentation     Oct 2015 - Apr 2016

 

Follow-up project:

  • Complete rebuilt paper machine PM10 (P00572)