Hamburger Spremberg - 1. Tambour
Mentioned below the key facts of the project:
Investment: 160 M € (paper mill and corrugated board section)
Start-up: 1st semester of 2005
Annual production: 265.000 tons white top liner and testliner
40.000 tons corrugated board in the adjacent processing plant
Planning contract:
Preliminary project and approval engineering for authority
Plant engineering for stock preparation and paper machine
(Basic and detailed engineering for precess and plant)
Coordination of corrugated board plant
Purchasing
Installation and start-up planning
Supervision of erection
Due Diligence Report
Scope of planning :
Engineering: approx. 50.000 h
Supervision of erection: approx. 12.000 h
Implementation period:
Engineering: 07/2003 to 09/2004
Realisation: 10/2004 to 05/2005