Hamburger Rieger GmbH - Spremberg - 2019
Client: Hamburger Rieger GmbH, paper mill Spremberg, Germany
Erection containerboard machine PM2
500.000 t/y net
Project
TBP received the order for the new construction of PM2 in the "Schwarze Pumpe" for the production of corrugated base paper (white and brown packaging papers). The waste paper yard was renewed, waste paper stock preparation incl. conveyor belts connected to the existing PM1, PM and RSM as well as ancillary equipment connected and connected to PM1, auxiliary stock storage renewed, finished roll storage incl. roll transport incl. the connection to the existing PM1 and corrugator, web unloading and loading, spare parts storage and roll storage as well as office building adjustments, connection of the pipe bridges to the power plant and the wastewater plant were made.
Planning contract
- Basic-engineering and submission planning
- Stock preparation
- Paper machine
- Auxiliaries
- Finished product process
- Detail-engineering
- Supervision of erection and start up
Project size
|
Investment sum |
456 Mio € |
Technical data
| Annual production capacity | 500.000 t/y |
| Total production capacity at Spremberg mill |
|
| Products |
Packaging papers (recycled container board (White Top Testliner, Coated Top Testliner)) |
| Working width | 7.800 mm |
Implementation period
| Basic-engineering and submission planning | May 2016 - Oct 2017 |
| Detail-engineering | Mär 2018 - Sep 2019 |
| Supervision of erection | Oct 2019 - Apr 2020 |
| Start up | Nov 2019 |
Related project:
- Submit change PM2 (P00857)