Hamburger Hungaria Kft. - Dunaújváros - 2009

Erection greenfield fluting and testliner machine PM7, Hungary

Client: Hamburger Hungaria Kft., Dunaújváros, Hungary

Erection greenfield fluting and testliner maschine PM7

350.000 t/y net


Project

TBP received the order for the general and construction planning of the new PM7. Included was from the preliminary project over the entire engineering up to the assembly supervision and start-up for the complete plant construction.

The plant design includes the waste paper yard up to the finished goods storage.

 

Planning contract

  • Pre-engineering and submission planning
  • Purchasing for equipment and E / I&C
  • Basic- and detail-engineering
  • Supervision and start up planning including supervision of erection and start up assistance
  • CE documentation

 

Project size

Investment sum                                   > 200 Mio €


Technical data

Annual production capacity                   350.000 t/y
Products

Packaging papers (recycled containerboard
(Corrugated medium, Testliner))
Working width 7.800 mm


Implementation period

Pre-project and submission planning     Nov 2006 - May 2007
Engineering Jun 2007 - Nov 2008
Supervison of erection and start up
assistance

Sep 2008 - Jul 2009
Start up Jun 2009