Client: Hamburger Hungaria Kft. (Hamburger Hungaria Power Plant), Dunaújváros, Hungary
Erection multi fuel power plant
158 MW/thermal / 45 MW/electrical
Project
TBP received the order for the entire plant engineering for the construction of a new biomass steam power plant with combined heat and power of 158 MW/thermal and 45 MW/electrical.
Planning contract
- Project management and procurement for the entire plant
- Process and plant planning for overall plant, i.e.
- Process, layout, piping, electrical, instrumentation and automation
- Construction planning for entire plant (by subcontractor BHM Ingenieure)
- Authority engineering and submission (package suppliers for boiler and turbine)
Project size
| Investment sum | 141 Mio € |
Technical data
| Output | 158 MW/thermal |
| 45 MW/electrical | |
| Steam capacity | 223 t/h |
| Steam pressure | 112 bar |
| Steam temperature | 520° C |
| Products | Steam, boiler circulation fluidized bed |
| Type of turbine | Extraction and condensing turbine |
Implementation period
| Purchasing | Mar 2012 - Dec 2012 |
| Basic-engineering and submission planning | Jan 2013 - Dec 2013 |
| Detail-engineering | Oct 2013 - Mar 2015 |
| Supervision of erection | Dec 2014 - Jun 2015 |
| Start up | Jun 2015 |