Cartones Yaguareté S.A. - Villeta - 2009

Plant relocation from Oftringen (Switzerland) to Villeta (Paraguay)

Client: Moritz J. Weig GmbH & Co. KG, Mayen, Germany   

Plant relocation from Oftringen (Switzerland) to Villeta (Paraguay)

60.000 t/y net (after relocation)



Project

TBP received the order to relocate the "Argovia PM4" for the production of containerboard paper and plaster board from Oftringen (Switzerland) to the plant in Villeta (Paraguay) as PM7. The recording work in the black plant involved the mechanical recording of the stock preparation and in the area of the PM vacuum system, fresh water supply and starch preparation as well as the electrical and I&C recording for the complete machine. New planning of PM7 at the Villeta site with the entire basic- and detail-engineering process, systems and E / I&C.


Planning contract

  • Recording work Oftringen (mechanical and E / I&C)
  • Dismantling
  • Basic- and detail-engineering Villeta (process, systems and E / I&C)
  • Supervision of erection


Technical data

Production after reloaction                     60.000 t/y
Products

Packaging papers (recycled containerboard),
Board (Plastic board liner (PBL))


Implementation period

Dismantling Oftringen (Switzerland)       Jul 2006 - Oct 2006
Engineering Villeta (Paraguay) Dec 2006 - Dec 2008
Installation Oct 2007 - Jul 2009
Start up stock preparation Apr 2009
Start up cardboard machine Jul 2009



Related projects:

  • E / I&C on-site recording (P4471)
  • Mechanical on-site recording (P4472)