AS Estonian Cell - Kunda - 2007

Project control for erection BCTMP plant, Estonia

Client: Heinzel Holding AG, Vienna, Austria  

Project control for erection BCTMP plant


Project

TBP received the order to carry out the project controlling for the new construction of the BCTMP plant. The EPC contractor's project documents were used exclusively for this purpose so that the submission to the financing banks could be checked.


Planning contract

  • Project contolling

    • Detailed description of work progress in the activities (planning, procurement, production, delivery to site, construction, assembly, testing and commissioning)
    • Creation of status diagrams (in accordance with EPC contract (planning, procurement, production and assembly))
    • Progress comparison
  • Bank report


Project size

Investment sum for
erection BCTMP plant                    


approx. 48 Mio €

Control period 18 months


Technical data

possible production 140.000 t/y net
possible production capacity                480 t/d net
  (at 100 % capacity utilization and valid for
small quantities of printed matter)
Product Graphic papers (Printing paper)


Implementation period

Admission and documentation          2004 - 2006
Bank report final May 2007