Agrana Zucker GmbH - Tulln - 2015

Expansion molasses desugaring, Austria

Client: Agrana Zucker GmbH, Tulln, Austria

Expansion molasses desugaring 

Molasses production increase to 85.000 t/y net


Project

TBP received the order for the expansion to increase molasses processing from 70.000 t/y to 85.000 t/y, by adapting the as-built flowsheet for agency submittal. Review of inventory pumps, piping ratings and fittings. Preparation of basic data list for instrumentation and the process description for authority submission.


Planning contract

  • Basic-engineering and submission planning
  • Detail-engineering and tender for construction and plant engineering services
  • Supervision of erection
  • Start up assistance


Project size

Investment sum                                                 15 Mio €


Technical data

Production increase                                    540.000 t/y
Products Natural betoine molasses (Actibeet®)

 

Implementation period

Engineering     Apr 2014 - Okt 2014
Dismontling Jun 2014 - Jul 2014
Construction phase Jul 2014 - Aug 2014
Supervision of ererction and start up monitoring              Aug 2014 - Feb 2015
Start up Feb 2015