PLANTENGINEERING
Agrana Zucker GmbH - Tulln - 2015
Expansion molasses desugaring, Austria
Client: Agrana Zucker GmbH, Tulln, Austria
Expansion molasses desugaring
Molasses production increase to 85.000 t/y net
Project
TBP received the order for the expansion to increase molasses processing from 70.000 t/y to 85.000 t/y, by adapting the as-built flowsheet for agency submittal. Review of inventory pumps, piping ratings and fittings. Preparation of basic data list for instrumentation and the process description for authority submission.
Planning contract
- Basic-engineering and submission planning
- Detail-engineering and tender for construction and plant engineering services
- Supervision of erection
- Start up assistance
Project size
| Investment sum | 15 Mio € |
Technical data
| Production increase | 540.000 t/y |
| Products | Natural betoine molasses (Actibeet®) |
Implementation period
| Engineering | Apr 2014 - Okt 2014 |
| Dismontling | Jun 2014 - Jul 2014 |
| Construction phase | Jul 2014 - Aug 2014 |
| Supervision of ererction and start up monitoring | Aug 2014 - Feb 2015 |
| Start up | Feb 2015 |